Current & Voltage Measurement in EV Battery Charging

On-board chargers and DC fast charging: PFC, DC-link, isolated DC/DC conversion, battery-side measurement, bidirectional charging and safety requirements.

ADISENS Technical KnowledgeWeb article
TECHNICAL OVERVIEW

Two charging architectures — different sensing priorities.

EV charging is built around two main power-conversion arrangements: an on-board charger (OBC), which converts AC from the grid inside the vehicle, and an external DC fast charger, which performs the conversion in the charging station and supplies regulated DC directly to the traction battery.

AC CHARGING

On-board conversion

The vehicle contains the rectifier/PFC stage and isolated DC/DC converter. Typical charging power is around 3.7–22 kW depending on the vehicle and supply.

DC FAST CHARGING

Off-board conversion

High-power PFC and isolated DC/DC stages are located in the charger. Power can range from about 50 kW to several hundred kilowatts.

01 · ON-BOARD CHARGER

AC grid → PFC → DC link → isolated DC/DC → battery

AC grid
→
PFC rectifier
→
DC link
→
Isolated DC/DC
→
Vehicle battery

The input-current measurement supports power-factor correction and grid-side overcurrent protection. DC-link voltage is monitored between the PFC and DC/DC stages, while battery-side current and voltage close the charging-control loop.

02 · DC FAST CHARGER

Three-phase grid → high-power conversion → vehicle DC interface

3-phase grid
→
High-power PFC
→
DC link
→
Isolated DC/DC
→
DC output
→
EV battery

The architecture is functionally similar to an OBC but at much higher current. The charger must regulate output current and voltage precisely, supervise isolation before connection, and manage substantial thermal stress at high continuous power.

03 · MEASUREMENT POINTS

What each measurement is doing

AC input current

Used for PFC control and grid-side overcurrent protection in both OBC and DC-fast architectures.

DC-link voltage

Supervises the intermediate energy buffer and provides a control reference for the isolated DC/DC stage.

Battery-side current

Controls charge rate, supports battery protection and becomes bidirectional in V2G/V2H-capable systems.

Battery / output voltage

Ensures the charger stays within the battery's permitted voltage envelope and supports delivered-energy measurement.

Insulation monitoring

Before a DC fast charger connects to the vehicle, the floating DC output must be checked for adequate insulation to earth by the system's IMD function.

04 · BIDIRECTIONAL CHARGING

V2G, V2H and V2L change the measurement requirement.

When energy flows from the vehicle back to the grid, home or external load, battery-current measurement must remain accurate in both directions. Directional asymmetry, offset drift and long-term stability therefore become more important than in a purely unidirectional charging system.

Metering implication

Where exported energy has contractual value, the discharge-direction measurement can become part of the transaction chain and may be subject to market-specific legal-metrology requirements.

05 · COMPARISON

OBC and DC-fast charging impose different constraints

CriterionOn-board charger (OBC)DC fast charger
Typical power3.7–22 kW50–400 kW+
Typical output current16–32 A per phase on AC side125–500 A on DC output
Typical DC output voltage~200–500 V battery pack~200–1,000 V
Dominant integration constraintVehicle volume and thermal budgetHigh continuous current and outdoor operation
BidirectionalityIncreasingly commonStill less common
Specific safety focusVehicle galvanic isolationInsulation monitoring before connection
06 · STANDARDS

Electrical safety, interface and communication references

ReferenceDomainMeasurement relevance
IEC 61851 seriesConductive EV charging systemsCharging modes and general safety requirements
IEC 62196Plugs, socket-outlets and vehicle connectorsAC/DC interface definition
ISO 15118Vehicle-to-grid communicationDigital exchange of current and voltage limits
IEC 61000 seriesElectromagnetic compatibilityEmission and immunity of power-conversion equipment
IEC 60364-7-722Electrical installations for EV chargingSupply-circuit and residual-current protection
07 · ENGINEERING SELECTION

Sensor selection follows the measurement function.

High-power output

Continuous-current capability and thermal behaviour can be as important as static accuracy.

On-board integration

Compact size, production cost and thermal budget are major drivers inside the vehicle.

Billing / metering

Long-term stability and low thermal drift matter when output measurements contribute to billed energy.

Isolation & safety

Measurement architecture must be evaluated with the complete insulation and protection concept rather than as an isolated component choice.

ADISENS ENGINEERING

Translate the measurement requirement into the right sensing architecture.

Use the Product Selector for a first technical orientation, or share your electrical, mechanical and environmental constraints with our engineering team.